From the earliest stages, Trent and Tyne Gas Fields presented many challenges.
To reinvigorate this remote operation, Perenco opted to install booster gas compression.
Budgetary constraints required that an innovative solution be deployed. Perenco managed to halve investment by devising a self installing solution:
| Budget |
| 80 musd all inclusive |
| Time for delivery |
| 12 months |
| Incremental production |
50 mmscfd 40 bcf of reserves created |
• Deployment of a self-installing Mobile Offshore Application Barge (MOAB)
• Fully unmanned operation
• 2 x 60 mmscfd of compressed gas driven by low-emission turbines and power-generation unit
• Incorporation of third party gas tie-in points and risers
• Re-usable concept to minimise decommissioning costs